Expansion of the sewage treatment plant, as part of the program to adapt the production units of PGE GiEK Branch Elektrownia Turów, to the BAT conclusions

Investor
PGE Mining and Conventional Power Generation S.A. Turów Power Plant Branch
Location
Bogatynia
Scope of Work

The subject of the Contract was to carry out complete construction and assembly works including:

  • Buildings and cubic structures along with technical installations and equipment (installation for sulphate precipitation from concentrates node D, industrial wastewater treatment plant installation node E);
  • Adaptation of existing buildings and installations of the Ordering Party to the necessary extent to carry out the task;
  • Construction of sewage intakes from ash settling tanks OP I and OP II;
  • Construction of sewage discharge points to ash settling tanks OP I and OP II;
  • Execution of a pressure pipeline from the new gypsum warehouse MG-2 to ash settling tanks, along the route of the existing pipeline, with infrastructure allowing to reserve the existing pipeline with the newly built one;
  • Construction of equipment and tank foundations; construction of technological tanks; construction of technological channels; construction of sewers; roads, maneuvering areas, technological squares, parking lots, and sidewalks.